Rebuilding Place in the Urban Space

"A community’s physical form, rather than its land uses, is its most intrinsic and enduring characteristic." [Katz, EPA] This blog focuses on place and placemaking and all that makes it work--historic preservation, urban design, transportation, asset-based community development, arts & cultural development, commercial district revitalization, tourism & destination development, and quality of life advocacy--along with doses of civic engagement and good governance watchdogging.

Tuesday, May 23, 2017

Weaponization of EIS: the Purple Line

A few years ago I was at a conference on infrastructure, and I was talking to a journalist who reports on infrastructure financing for an institutional investing publication, and he referred to what he called "the weaponization of environmental review processes," in terms of how they (1) extend the development process to unbelievably long time frames and (2) provide multiple opportunities for people to file lawsuits against the project.

That's what's happened with the Purple Line light rail project in Montgomery and Prince George's Counties Maryland, where a lawsuit challenged the project's EIS--environmental impact statement--arguing that decline in Metrorail and Metrobus ridership because of the decline in the operating reliability of that system could have marked impacts on Purple Line ridership.

While the Maryland Transit Administration and the US DOT argued that WMATA ridership drops are not necessarily permanent and that the impacts are likely within normal ranges already considered, yesterday it was reported that federal Judge Richard Leon did not agree, calling for a revised EIS.

-- "Purple Line suffers major setback in Court," Washington Business Journal

Because of changes in federal priorities under the Trump Administration that disfavor transit, despite claims by Donald Trump as candidate and as President that he is committed to funding and implementing a wide-ranging infrastructure, delays increase the likelihood that federal funding will not happen, and the State of Maryland will stop funding the development phase of the project too.


Ironically, on Saturday, the Wall Street Journal had an article ("One Rail-Station Design May Be Just the Ticket to Ease Congestion") on a proposal by Rethink Studio in NYC to improve rail system reliability in Greater New York by better integrating and enhancing existing stations in the "station network" by improving and expanding connections between Penn Station in ways that make the lines "through lines" rather than Penn Station being a terminal station (comparable to how I have suggested that the MARC Penn Line and the VRE Fredericksburg Line be merged, to increase throughput, service, and decrease the demand for train storage in the Ivy City yard, see "A new backbone for the regional transit system: merging the MARC Penn and VRE Fredericksburg Lines).

-- Volume One, Regional Unified Network, Rethink Studio, NYC

That article uses Crossrail in London and the Regional Rail (RER) program in Paris, and the Center City Connection program in Philadelphia which connected separate Pennsylvania Railroad stations--Suburban Station and 30th Street Station--with the old Reading Railroad lines and Reading Terminal, as examples of how to increase railroad passenger train capacity by creating through lines through "elimination" of terminal end point stations.  From the article:
Terminal stations, where trains must reverse course to continue service, slow down travel. Through-running stations, where trains keep going without changing direction, speed it up.

The difference affects how many people can funnel into a busy urban core during peak hours or pass through the city to reach other destinations. For that reason, many metropolises opt for through-running stations.
I argued from a slightly different perspective that the Purple Line, by providing a critical east-west medium capacity, high frequency rail line that connects the East and West legs of the Red Line, the north leg of the Green Line, and the east leg of the Orange Line, can have a similarly positive impact on Metrorail, by reducing the need for people to travel to and from Downtown DC in order to transfer between lines for trips that originate or end in Suburban Maryland.

Plus, the Purple Line will connect to all three lines of the MARC passenger rail system, the Brunswick Line in Silver Spring, the Camden Line in College Park, and the Penn Line in New Carrollton, further increasing the utility and benefit of the rail system as a more integrated network.

(In "Setting the stage for the Purple Line light rail line to be an overwhelming success: Part 2 | proposed parallel improvements across the transit network" I proposed a parallel and complementary set of improvements across the transit network in concert with the development of the Purple Line, to further increase the value of the transit network.)

Not to mention that because of congestion and rail-induced development ("transit oriented development") a larger proportion of dense development in the metropolitan area is constructed in transit station catchment areas.

Plus, it is likely that despite competing objectives and goals amongst the jurisdictions, WMATA will be "fixed" and ridership will recover a significant proportion of the current decline -- which has also been abetted by lower gasoline costs and continued subsidy of driving in various ways.

We must remember that the NYC Subway system suffered grievous declines in the 1970s and 1980s but recovered.  In fact, the system's current problems are a result of an explosion of ridership and the need to invest in physical improvements including technology advances and storm-related resiliency measures ("MTA Announces 6-Point Plan to Restructure Management and Improve System Reliability," MTA).

I am not a lawyer, and I didn't read the arguments and submissions on the court case -- from the WBJ article:
In the 12-page memorandum, Judge Richard Leon wrote that Maryland and federal officials must produce a supplemental environmental impact statement "as expeditiously as possible." The ruling is an extension of what Leon told the parties in November, when he declined to reinstate the Purple Line Record of Decision, a federal environmental document that would allow construction on the $5.6 billion project to proceed.

This all comes in a response to a complaint from a Chevy Chase citizens group, Friends of the Capital Crescent Trail, that has been in the courts since 2014.

"In effect, FTA boldly concluded that there is no need for an SEIS, and the Purple Line will meet its established purposes, no matter what happens to WMATA Metrorail," Leon wrote. "To say the least, this is a curious conclusion when one considers that one of the three explicit purposes identified for the Purple Line was to 'provide better connections to Metrorail services.'"
but I believe that Judge Leon erred in his holding--although I can understand his reasoning--and it is unfortunate that this holding significantly increases the likelihood that the Purple Line will not move forward, and for all the expressed concern about "the environment," "sustainability," "climate change and global warming," and "greenhouse gas emissions," the reality is that the automobility and oil-dependent mobility paradigm continues to reign supreme.

Weaponization of EIS indeed.   Note that I do agree with critics that the EIS process can be unduly time consuming, at significant cost to doing important projects.  In large part this is because it provides many opportunities for opponents to sue or otherwise influence stakeholders to back down.

It certainly discourages "the private sector" from bidding on and investing in such projects if there is always a high degree of uncertainty due to the possibility of lawsuits and unfavorable decisions.

Labels: , , , , , ,

Wednesday, June 27, 2012

Revisited: Private financing of public infrastructure is good business for business

Below is the reprint of a blog entry from August 2011, about private sector financing of public infrastructure, usually transportation projects.  It's relevant to the announcement that DC has released a "request for information" from companies and other interested parties willing to consider financing, constructing, and operating DC's proposed streetcar system, along with the small city bus system (the Circulator) that operates independently of the WMATA Metrobus system.  See "DC wants input on privatized streetcar system" from the Washington Post and the RFI document from DDOT.

The thing about the project is that I don't see what the advantage is for a company to finance a streetcar system, because it isn't "profitable" from the standpoint of fare revenue being great enough to pay for operations and pay for the cost of capital to build the system.

This isn't the case for parking meters (see "New York to Repeat Chicago’s Parking Meter Catastrophe" from the Rolling Stone), speed and traffic light cameras, and toll roads (mostly, some of the deals are losers from the standpoint of the private sector)--in most cases, especially if the value of the asset is significantly underpriced, as it was in Chicago with regard to the parking meters there (see the blog entry "A lesson to cities that they need to be very careful when leasing assets to public private "partnerships""), the revenues are greater than the cost to build, finance, and operate the system.  That's why the private sector, with capital from other nations usually, is so eager to do these deals.

Most of the involvement of the "private sector", which as Taras Grescoe points out in Straphanger, the companies involved in third party operation of transit systems in North America typically are divisions of European "companies" that are in part, government entities, is in operating transit systems under contract to local and regional governments.

Usually, private companies can do this at a profit because they don't pay as much or offer as good a benefit package compared to "straight-up" government jobs, and they tend to have fewer employees overall to run the system. 

Note that the strike in the Phoenix area bus system was about penalty payments for service failures being "so high" that it prevented the company from giving raises to unionized employees.  So the union struck in order to pressure the City of Phoenix to change the contract with the operator, Veolia Transportation.  See the blog entry "Sunday March 18 is International Bus Driver Appreciation Day."

This can be one of the downsides about "privatization" of transit services.

However, it could be that that the profit stream is high enough to make it worth "buying," through the funding of the construction of the system.  My expertise in financial engineering isn't deep enough to be able to figure that out.

To illustrate the idea of "buying a profit stream," Ohio State University has just done a 50 year lease of its parking operations.  Figuring out what they get upfront, a payment of $483 million, which they intend to invest and reap about $3 billion in total, the amount isn't much different than if they continued to operate the system themselves.  (net present value vs. revenues over 30 years)

The difference is that they get the investment capital upfront and don't have to manage and operate something that clearly is an ancillary activity in the context of their mission as a degree-granting research university.  See "Ohio State University Trustees Approve 50-Year Parking Lease" from the Wall Street Journal.


------------------
Reprinted blog entry from August 2011

Face it, the reason that private outfits finance public projects, buy toll roads, fund traffic cameras, etc., is because there is money in it.

But it comes at a cost, because if the projects had been funded with public monies, all of the monies spent would have gone to the projects, rather than to financing, administration, and private profit.

The Financial Times has a big article on the topic, "Public finances: A divisive initiative" and an editorial, "Building debts for the future."

From the article:

“I first really began to worry about the private finance initiative back in 2003,” says Mr Bacon. “I ran into an investment banker who said: ‘I like the PFI [Private Finance Initiative]. It’s good for business. We make a lot of money out of it. But as a taxpayer, it really cheeses me off.’ That rather woke me up. This was not a trade unionist complaining. It was a City fat cat getting fatter on the proceeds.” ...

Why has it proved to be so popular? “For three reasons,” a former Treasury adviser says. “Governments think it transfers risks, and works. Because they don’t have to raise the capital now. And because accounting rules mean it often does not count on the government’s books. You make your own judgment over which is the main driver,” In other words, for at least two of those reasons, governments simply cannot resist it.

After all, private borrowing costs more than government borrowing. And while any government borrowing would be written off if the school or hospital were no longer needed, under PFI the taxpayer would also have to cover the lenders’ anticipated profit. So once a PFI contract is signed, it is almost impossible to get out except at enormous expense.

In theory the transfer of risk, and the efficiencies gained, more than pay for the extra borrowing costs. But these are not small. ... Calculations by the Financial Times suggest that, on the £53bn capital value of current PFI projects, that translates to the taxpayer having to pay £20bn-£25bn above the government borrowing rate – the equivalent of 40 or so big hospitals. “You need an awful lot of risk transfer or efficiency gain to make that worthwhile,” Mr Bacon says.


The editorial closes with this paragraph:

PFI has created an export industry. It is a nice business for the City, employing armies of bankers and consultants. But it is not the taxpayers’ job to provide a living for these people. A new approach is required. Before signing more PFI deals, the government should show that the same project could not have been delivered with better value for money had it been financed directly by the state.

Also from the Financial Times:

-- "Watchdog calls for alternative to PFI"
-- "PFI profits ‘not shared by the taxpayer’"
-- "MPs hear of PFI profit-share potential" (this article suggests that the public sector should get a cut of the appreciation when such public-private assets are sold)

-- UK National Audit Office, section on Private Finance

Labels: , , ,

Saturday, December 17, 2011

Master planning and DC's Union Station intermodal transportation center

Capitol Plaza, looking north towards Union Station
Last week the City Paper had its cover story on Union Station, "A More Perfect Union Station: D.C.'s Train station is a mess; again."

Basically, the problem is that Union Station is owned by the federal government and was handed off to a "public-private" partnership (3P in the trade), with minimal public oversight and limited local involvement.

The book I mentioned in a previous entry, A Negotiated Landscape by Jasper Rubin, about the San Francisco waterfront, makes a point that I found very relevant to thinking about DC.

In the 1800s development and management of the San Francisco Waterfront had a lot of corrupt elements to it. So the State of California took the waterfront over, creating a port authority that had limited involvement from the locals, thus separating management control of the waterfront from the people that had the most interest in it--not just capital and political interests that may have been willing to manipulate, lie, cheat and steal to serve their interest, but community and civic interests as well.

That's the fundamental problem with Union Station--its management is federal/disconnected, but for the most part the building's importance concerns its use as a key node in the local transportation system.

Yet Union Station is used by upwards of 65,000 daily commuters (there's double counting, because some railroad passengers use the subway), it's a shopping center for residents and nonresidents, it's the most used civic asset in the city, it's one of the key transportation nodes in the region, and it's a beautiful building that anchors the city.

First, if its oversight is federal, by definition it's disconnected from local concerns. Second, as in too many of these creations, the 3P was created but I don't think they were required to create a master plan through a public process. Third, they weren't required to update a master plan on a regular basis.

So there is no master plan for Union Station. And if there were there might not be all that much local input into it. Meaning, it might not be that good.

Chicago Union Station improvement program
Last week, the City of Chicago released a master plan for its Union Station. See "New master plan emerges to transform Union Station" from the Chicago Tribune. From the article:

The goals to create a more vibrant terminal that can be a catalyst for growth in the West Loop include:

•Expanding capacity to handle more trains and relieve congestion to make today's crowded concourses and mezzanines more inviting. Union Station handles more than 300 trains each weekday carrying more than 120,000 arriving and departing passengers.

•Building an off-street CTA bus terminal on the existing surface parking lot south of Jackson Boulevard; and providing more convenient transfers to CTA trains as well as taxis and shuttles.

•Launching an east-west bus rapid transit service from Union Station to Michigan Avenue and eventually Navy Pier.

•Easing potentially dangerous conflicts with vehicles, pedestrians and bicyclists by reconfiguring how Canal Street is used.


The article discusses visions to build a new mixed use station and incorporating high speed train service.

-- Chicago Union Station Master Plan website
-- Union Station: Chicago's Downtown Airport, Midwest High Speed Rail Association
High speed rail vision for a downtown Chicago train station.  Illustration provided by Solomon Cordwell Buenz
High speed rail vision for a downtown Chicago train station. Illustration provided by Solomon Cordwell Buenz.

The difference between Chicago's Union Station and DC's is that their station is less connected to the city subway and transit system compared to ours, and the focus is more on railroad transportation.

Note that Denver has done similar kind of master planning, although more focused on having their Union Station as the downtown hub for their regional light rail system.

Not having a master plan for DC's Union Station means that it's taken almost 10 years to ink a project for improving the area in front of the system.

It's taken 20 years to get inter-city bus services integrated into Union Station.

Amtrak went ahead with plans that make it difficult to integrate streetcar service into Union Station.

Connections between the railroad train platforms and the subway station are in serious need of improvement, although a separate planning initiative is addressing that, and according to the City Paper article, Union Station has hired Lance Wyman (designer of the WMATA map) to do wayfinding, although the issues are more considerable and include cultural interpretation as well as making connections to other nearby districts, as well as providing transit and tourist travel wayfinding and interpretation as well.

Master plan...

P.S., master planning "Union Station" needs to include BeyondDC's point that additional train stations in the city and Arlington County, Virginia should be developed, in order to improve service and reduce the over-demand issues created at Union Station because the trains stop and start there, rather than going through.


Intercity Travel:
Union Station will be past capacity and we will need a second depot, possibly in Arlington. There will be multiple trains per day running several short-distance intercity rail trips to all other population centers in the mid-Atlantic region. Camden Station will become more important in Baltimore. Dulles and BWI airports will continue to expand. National Airport may be sold and the land redeveloped, or it may continue to operate, depending on how much intercity travel continues to be done by plane.

Labels: , , ,

Wednesday, August 10, 2011

Private financing of public infrastructure is good business for business

Face it, the reason that private outfits finance public projects, buy toll roads, fund traffic cameras, etc., is because there is money in it.

But it comes at a cost, because if the projects had been funded with public monies, all of the monies spent would have gone to the projects, rather than to financing, administration, and private profit.

The Financial Times has a big article on the topic, "Public finances: A divisive initiative" and an editorial, "Building debts for the future."

From the article:

“I first really began to worry about the private finance initiative back in 2003,” says Mr Bacon. “I ran into an investment banker who said: ‘I like the PFI [Private Finance Initiative]. It’s good for business. We make a lot of money out of it. But as a taxpayer, it really cheeses me off.’ That rather woke me up. This was not a trade unionist complaining. It was a City fat cat getting fatter on the proceeds.” ...

Why has it proved to be so popular? “For three reasons,” a former Treasury adviser says. “Governments think it transfers risks, and works. Because they don’t have to raise the capital now. And because accounting rules mean it often does not count on the government’s books. You make your own judgment over which is the main driver,” In other words, for at least two of those reasons, governments simply cannot resist it.

After all, private borrowing costs more than government borrowing. And while any government borrowing would be written off if the school or hospital were no longer needed, under PFI the taxpayer would also have to cover the lenders’ anticipated profit. So once a PFI contract is signed, it is almost impossible to get out except at enormous expense.

In theory the transfer of risk, and the efficiencies gained, more than pay for the extra borrowing costs. But these are not small. ... Calculations by the Financial Times suggest that, on the £53bn capital value of current PFI projects, that translates to the taxpayer having to pay £20bn-£25bn above the government borrowing rate – the equivalent of 40 or so big hospitals. “You need an awful lot of risk transfer or efficiency gain to make that worthwhile,” Mr Bacon says.


The editorial closes with this paragraph:

PFI has created an export industry. It is a nice business for the City, employing armies of bankers and consultants. But it is not the taxpayers’ job to provide a living for these people. A new approach is required. Before signing more PFI deals, the government should show that the same project could not have been delivered with better value for money had it been financed directly by the state.

Also from the Financial Times:

-- "Watchdog calls for alternative to PFI"
-- "PFI profits ‘not shared by the taxpayer’"
-- "MPs hear of PFI profit-share potential" (this article suggests that the public sector should get a cut of the appreciation when such public-private assets are sold)

-- UK National Audit Office, section on Private Finance