Just a reminder that what are called "public private partnerships" are contracts, not partnerships
-- "Design-Build Team Makes Decision to Leave Maryland Purple Line Rail Project," Engineering News-Record
The State of Maryland signed a contract with a group of various firms to design, build, operate, maintain and partly finance the forthcoming Purple Line light rail line in Suburban Maryland. In turn, the group created a separate subsidiary to construct the line.
Washington Post graphic showing the route of the line.
There are various disputes between the State and the consortium over delays and changes that result in greater costs and who is responsible for paying.
Because negotiations up to now haven't resulted in resolution, the construction firm has given notice per the contract to walk away.
Um, despite all the happy talk about "public private partnerships," in normal circumstances, that's not how "partnerships" are supposed to work.
Although this is not new. The reality is that these are contractual agreements, and very hard to change once underway. And as contracts, there is little interest in flexibility and changes and improvements once the construction is underway.
From "The Theory and Practice of Infrastructure Public-Private Partnerships Revisited: The Case of the Transportation Sector":
PPPs are widely promoted based on a narrative of improved collaboration between different stakeholders. By aligning the interests of the multiple parties to encourage closer and more productive working relationships, it is argued that public-private partnerships support innovative project designs and deliver value for money by better controlling project risks. Despite the promises, however, relationships between the various partners in PPPs have often turned from collaborative to confrontational, threatening the success of the project.
This is reality. And as a result, I think it's better to call these kinds of arrangements contracts, not partnerships.
I was trying to hook up with one of the teams that bid on this project. They didn't win. And the experience led them to abandon future efforts on such large scale projects (although the firm remains one of the nation's largest construction firms).
One of the problems with projects like this is that they are so few and far between (the same goes with manufacturing passenger transit vehicles of all types) that it's hard to build economies of scale.)
And early on in the post-bid acceptance process, I learned there was no room for innovative station area planning and development, etc., because "it's not in the contract."
-- "A Purple Line update: the downside of Public Private Partnerships" -- they are contracts, not partnerships," 2017
-- "It's not like transit "outsourcing" I mean "public-private partnerships" are necessarily smooth sailing," 2018
Which is one of the reasons why my brilliant writings around the Purple Line will have no effect.
-- "Revisiting the Purple Line (series) and a more complete program of complementary improvements to the transit network," 2019
-- Setting the stage for the Purple Line light rail line to be an overwhelming success: Part 1 | simultaneously introduce improvements to other elements of the transit network
-- Part 2 | the program (macro changes)
-- Part 3 | influences
-- Part 4 | Making over New Carrollton as a transit-centric urban center and Prince George's County's "New Downtown"
-- PL #5: Creating a Silver Spring "Sustainable Mobility District"
-- Part 6 | Creating a transportation development authority in Montgomery and Prince George's County to effectuate placemaking, retail development, and housing programs in association with the Purple Line
-- Part 7 | Using the Purple Line to rebrand Montgomery and Prince George's Counties as Design Forward
-- PL #5: Creating a Silver Spring "Sustainable Mobility District"
- Part 1: Setting the stage
- Part 2: Program items 1- 9
- Part 3: Program items 10-18
- Part 4: Conclusion
- Map for the Silver Spring Sustainable Mobility District
- (Big Hairy) Projects Action Plan(s) as an element of Comprehensive/Master Plans
- Creating the Silver Spring/Montgomery County Arena and Recreation Center
Labels: civil engineering, contract administration, development and construction, infrastructure, public private partnerships (3P), transit design and engineering